How to Implement CBM with ISO 17359: A Plant Manager's Step-by-Step Guide

Alex Vedan

Updated Nov 23, 2026

10 min.

Key Points

  • ISO 17359:2018 sets out the order of work for a condition monitoring program, starting with the business case.
  • Owners, inputs and outputs for each step turn the standard into a plan a plant manager can staff and fund.
  • Continuous monitoring with AI diagnosis carries the measurement, diagnosis and maintenance hand-off steps.

ISO 17359 condition based maintenance starts with a cost-benefit case and ends with a review and training loop, with the equipment audit, criticality ranking, monitoring design and diagnosis in between. Following that sequence puts sensor and labor budget on the machines that stop production, which is the spend a CFO will question first.

Each of the eight steps of ISO 17359:2018 is filled in below for one example plant, with the owner, the input, the output and a realistic duration, plus the metrics that show leadership the program is paying back.

What is ISO 17359 and why does it matter for a CBM program?

ISO 17359:2018, "Condition monitoring and diagnostics of machines: General guidelines," is the international guidance for setting up a condition monitoring program for machines. The current text is the third edition, published in January 2018 and reviewed and confirmed by ISO in 2023.

It matters because it gives a condition-based maintenance program a defensible order of work. The standard ties monitoring to the root-cause failure modes of each machine, then covers alert criteria, diagnosis, prognosis and how to raise confidence in a diagnosis.

ISO 17359 is also the parent document of a family of machine condition monitoring standards. It points to ISO 13379-1 for data interpretation, ISO 13381-1 for prognostics and ISO 20816 for vibration evaluation, and the 2018 edition added a reference to the ISO 55000 asset management series. For a plant manager, that means one framework to show auditors, insurers and the leadership team.

What are the ISO 17359 steps, in plain terms?

ISO 17359 lays out eight steps: cost-benefit analysis, equipment audit, reliability and criticality audit, monitoring method, data acquisition and analysis, determining the maintenance action, review, and training. The first four decide what to monitor and why; the last four run the program week to week.

  1. Cost-benefit analysis: put a dollar value on failures and on the program that would catch them.
  2. Equipment audit: list the machines and what each one does in the process.
  3. Reliability and criticality audit: rank machines by consequence of failure, map failure modes, and pick a maintenance task for each one.
  4. Monitoring method: choose the measurements, intervals, measurement locations, first alert limits and baseline readings.
  5. Data acquisition and analysis: collect and trend data, compare it to alert limits, then diagnose and estimate remaining life.
  6. Determine maintenance action: decide what to do, by when, and log it.
  7. Review: check results against the business case and adjust limits, methods and coverage.
  8. Training: give the people who collect, read and act on the data the skills their part needs.

The table fills those steps in for one example plant. The plant and its figures are illustrative, built to show what each step produces; they are not Tractian customer data.

ISO 17359 step (example plant) Owner Input Output Example duration Where continuous monitoring helps
1. Cost-benefit analysis Plant manager with the plant controller 46 unplanned corrugator hours last year, $9,000 of output lost per hour, emergency repair invoices $414,000 annual downtime exposure and a target for hours to convert into planned stops 1 to 2 weeks Later, measured avoided hours replace estimates in the case
2. Equipment audit Maintenance planner CMMS asset register, P&IDs, nameplates Clean list of 380 machines, each with its process function 2 to 3 weeks Not much yet: the register is desk and floor work
3. Reliability and criticality audit Reliability engineer with production and maintenance leads Equipment list, failure history, line layout 64 critical machines, 22 on the corrugator path, failure modes and a task per machine About 3 weeks Sensor history later sharpens each re-ranking
4. Monitoring method Reliability engineer Failure modes per machine, access, operating states Measurement plan: technique, interval, location, first alert limits, baseline 1 to 2 weeks Wireless sensors cut the interval from a route schedule to minutes
5. Data acquisition and analysis Reliability engineer, with AI diagnosis doing the first pass Sensor data from the 64 critical machines Trends, alerts against limits, a diagnosis and a severity for each finding Install in a day, full visibility in about 14 days, then ongoing Highest impact: data, trending and diagnosis run continuously
6. Determine maintenance action Maintenance manager and planner Diagnosis, severity, production schedule, spares on hand Work order in the CMMS with a due date tied to severity Per finding, within the planning cycle Findings arrive with a recommended action and flow to the CMMS
7. Review Plant manager Alert check-in rate, findings, avoided hours, false alarms Updated limits, coverage changes, a dollar report for leadership One check a month, a business review each quarter Dashboards and BI connectors pull the numbers without a spreadsheet hunt
8. Training Maintenance manager Roles in the program, skills gaps by shift Named platform users per shift who know how to read and close an alert During rollout, then with each new hire Plain-language alerts lower the skill needed to act on a finding

Example plant (illustrative): a two-line corrugated packaging plant where one corrugator feeds both converting lines. Durations are examples for this plant, not requirements of the standard.

What does each step look like in one plant?

In the example plant, steps 1 to 4 take about seven to ten weeks of desk and floor work, led by the plant manager and a reliability engineer. Steps 5 to 8 then run continuously. The detail below shows what each step produces and the decision it hands to the next one.

Step 1: Cost-benefit analysis

ISO 17359 puts the business case first, before any sensor is chosen. The plant manager needs one number the controller will accept: annual downtime cost = unplanned downtime hours x production value lost per hour.

In the example plant, the corrugator lost 46 unplanned hours last year at $9,000 of output per hour, so the exposure is $414,000 before repair invoices. If earlier warning turns 20 of those hours into planned stops, the program protects $180,000 a year in output alone. Learn more about CBM ROI.

Add secondary damage to the case. A single facer bearing that seizes can score the roll journal it sits on, turning a parts-bin repair into a machine shop job and a multi-shift outage.

Step 2: Equipment audit

The equipment audit lists each machine and the function it performs in the process. The maintenance planner starts from the CMMS asset register, then walks the floor to correct it against nameplates and drawings.

The output is a register the rest of the program can trust. In the example plant, the walk-down turns up duplicate records and two vacuum blowers missing from the register, which would have left the single facer's vacuum supply outside the program.

Step 3: Reliability and criticality audit

This step ranks machines by what happens when they fail and identifies how they fail. ISO 17359 points to reliability block diagrams, an equipment criticality ranking and FMECA as the tools.

A criticality analysis in the example plant puts 64 of 380 machines in the critical class, 22 of them on the corrugator path: main drive gearbox, single facer, preheater roll drives, vacuum blowers and the boiler feed pumps that supply steam. For each one, the team records the failure modes that matter, such as bearing wear, gear tooth damage, misalignment and lubrication loss.

The same step chooses the maintenance task for each machine. ISO 17359 calls these alternative maintenance tasks: condition monitoring where a failure gives warning, time-based replacement where it does not, and run-to-failure for cheap, redundant items like a spare exhaust fan.

Step 4: Choose monitoring methods and measurement points

Step 4 matches each failure mode to a measurement that can detect it. ISO 17359 asks for the technique, its accuracy, the operating conditions during measurement, the monitoring interval, the data acquisition rate, the measurement locations, the first alert limits and a baseline.

For the corrugator gearbox, gear tooth damage shows up in vibration, while early lubrication loss shows up in ultrasound and temperature. Measurement points sit on the bearing housings closest to the load path. First alert limits often start from vibration alarm thresholds in ISO 20816 and are then tightened against each machine's own baseline.

The monitoring interval is where budgets get decided. A monthly route catches a failure when its warning period is longer than a month. A wireless sensor that samples in minutes moves that decision from labor hours to sensor coverage.

Step 5: Data acquisition, analysis and alert criteria

Step 5 collects the data, trends it, compares it to the alert limits, and then diagnoses the cause and estimates how long the machine can keep running. ISO 17359 also asks the team to check measurement quality and to raise diagnostic confidence before acting.

False alarms belong in this step. Pulling a healthy corrugator drive offline for a false alarm costs the same $9,000 an hour as a real failure, so a plant manager should track the false-alarm rate as closely as the detection rate.

Step 6: Decide the maintenance action

Step 6 turns a diagnosis into a dated job. The maintenance manager weighs severity against the production schedule and spares on hand, then the planner books the work in the CMMS for the next planned stop or sooner.

A finding with no work order is the CBM version of pencil whipping: the record says someone looked, but nothing changed on the machine.

Step 7: Review and improve

The review step checks the program against the business case from step 1 and adjusts it. In the example plant, the plant manager reviews alert response monthly and reports avoided hours and repair spend to leadership each quarter.

Reviews also change the plan. Limits that alarm too often get tightened to the machine's baseline, failure modes that slipped through get a new measurement, and machines that hold steady for several quarters get moved to a longer interval.

Step 8: Train the people who act on the data

ISO 17359 closes with training: the people who measure, interpret and act need the skills for their part. For a plant manager, that means named users on each shift who know how to read an alert, check the machine and close the loop in the CMMS. Learn more about building a CBM program.

How long does an ISO 17359-aligned rollout take?

A rollout has two clocks. The planning steps (business case, equipment audit, criticality audit, monitoring method) took the example plant seven to ten weeks. The monitoring steps start when sensors go on, and with wireless sensors that part takes days.

For a condition monitoring program on Tractian, install takes a day: no cabling to run, no IT project, and no reliance on plant WiFi. Full visibility follows within the first 14 days while the models learn how each machine runs. The planning work can also run in parallel: sensors go on the obvious bottleneck machines while the full criticality audit finishes.

How do you prove the program is working to leadership?

Report the program in dollars and in accountability. Leadership wants to see failures caught before breakdown, the production value those catches protected, and proof that the team acted on each alert.

  • Alert check-in rate: the share of alerts a technician opened, checked and closed. It is the plant manager's proof that findings turn into work.
  • Failures caught before breakdown: each one logged with the downtime hours it would have caused, priced at the plant's value per hour.
  • Secondary damage avoided: the repair cost difference between a planned bearing swap and a scored shaft or wrecked gearbox.
  • False-alarm rate: healthy machines taken offline because of a wrong call, priced the same way as downtime.
  • CapEx deferred: replacements pushed back because condition data showed the asset still had life in it.

Pirelli's tire plant offers a reference point. Tractian helped the plant reach a 98% alert check-in rate with 77 failures identified, including a gearbox gear wear signal that led the team to an undetected oil leak, fixed with the preventive job pulled forward by a day.

Where does Tractian fit in an ISO 17359 program?

Tractian supports the monitoring, diagnosis and hand-off steps of an ISO 17359 program, steps 4 to 6 in this guide, and feeds the numbers for the review step. The business case, equipment audit and criticality ranking stay with the plant team; Tractian makes the steps that depend on data run continuously.

Monitoring method. A Smart Trac Ultra sensor mounts on each critical machine and measures vibration, ultrasound, temperature and RPM on that asset. Sensors are Class I Div 1 ATEX/IECEx/NFPA compliant and connect sensor to receiver, receiver on 4G/LTE. For motor-driven machines, Energy Trac installs in the electrical panel that feeds the motor and tracks current, voltage and power factor to catch rotor, stator, winding and insulation faults.

Diagnosis. Combining Smart Trac Ultra and Energy Trac gives multimodal monitoring, with Janus, Tractian's industrial AI trained on proprietary data from real machines, learning how each asset normally runs under its load. Auto Diagnosis alerts state what's wrong, how severe it is and what to do, with evidence behind the call.

Maintenance action. Tractian focuses on condition monitoring and AI asset health. Each finding goes to the maintenance system already in place: MaintainX, Fiix, UpKeep or Limble for work orders, SAP or Oracle NetSuite for the ERP record. The integrations run via API, and Power BI and SQL connectors give the review step custom reports without exporting data by hand.

Tractian pricing is per monitored asset. Tell Tractian which machines from the criticality audit you want to protect, and a specialist will prepare a custom quote. Across 2,000+ operations, Tractian has returned $1.6B in avoided losses.

Frequently Asked Questions

What does ISO 17359 cover?

ISO 17359 gives general guidance on how to build a machine condition monitoring program. It covers the cost-benefit case, equipment and criticality audits, choosing monitoring methods, data analysis and diagnosis, deciding maintenance actions, review and training. It refers to other ISO standards for specific techniques such as vibration and tribology.

Is ISO 17359 a certification?

No. ISO 17359 is written as guidelines rather than requirements, so plants use it to structure a program rather than to earn a certificate. Plants that want third-party certification usually look at the asset management system standard ISO 55001 instead.

How does ISO 17359 relate to ISO 55001?

ISO 55001 sets requirements for an asset management system across the organization, while ISO 17359 describes how to run condition monitoring on machines. The 2018 edition of ISO 17359 references the ISO 55000 family, so a condition monitoring program built on it can feed the evidence an ISO 55001 system asks for.

Which assets should a CBM program start with?

Start with the machines whose failure stops production or causes expensive secondary damage, as ranked in the criticality audit. In most plants that means bottleneck drives, gearboxes, pumps, fans and compressors with no spare. Redundant, low-cost items can stay on time-based tasks or run to failure.

How often should a CBM program be reviewed?

ISO 17359 makes review a standing step but leaves the frequency to the plant. A practical rhythm is a monthly check of alert response and false alarms, plus a quarterly review of avoided downtime, repair spend and coverage against the original business case.

To see continuous monitoring and AI diagnosis on your critical machines, explore Tractian condition monitoring.

Alex Vedan
Alex Vedan

Director

Alex Vedan, Marketing Director at Tractian, develops impactful strategies that empower industrial clients across North America and LATAM to achieve operational excellence. By aligning innovation with customer needs, he ensures Tractian solutions drive meaningful improvements in efficiency and reliability.